Spring / Summer 2022 - Eversource Conducting Pre-construction Field Surveys & Assessments within Existing Powerline Corridor in Merrimack
Posted on: April 7, 2022 - 9:16am
This spring, Eversource’s Project Services division in conjunction with crews from Normandeau Associates will conduct pre-construction field surveys and assessments within the existing power line corridor in Merrimack and Amherst N.H. in preparation for replacing existing wood structures along the 3195 line.
3195 Maintenance T-Line Structure Replacements:
Schedule (subject to change): Archeological Testing: spring 2022, Civil Work: summer 2022, Line Work: fall 2022, Restoration: fall 2022-summer 2023
Phase 1b locations:
Merrimack: Peaslee Rd
Attachment | Size |
---|---|
220406_-_eversource_letter_3195_archeology_2022.pdf | 165.74 KB |